1 |
Comment:
|
2021-02-09 00:00:00 Comment: At random near Virk Niwas, the thickness of bedding sand under I/L tiles was checked and found in order.
Interlocking tiles being used were of correct thickness and were ISI marked. 45%
|
2021-05-25 00:00:00 Comment: Construction of Drain Type-II at park to Gandhi kariyana shop. Link Bathinda road.:-
1) The work for construction of drain was in progress.
2) The drain surface is not properly plastered. Plastering 70%
|
Comment: |