1 |
2020-12-31 00:00:00 Comment: Proposed site for P/L of 80 MM I/L tiles. 0%
|
2021-02-09 00:00:00 Comment: At the time of visit the laying of CC 1:8:16 was in Progress.
Thickness of base concrete was checked and found in order.
No Caution board & Night signals were displayed on work site & no cau 30%
|
2021-05-25 00:00:00 Comment: 1) Cement of ‘Shree’ make was being used at the site.
2) The thickness of bedding sand and base concrete under I/L 60mm tiles was randomly checked at 2 points near House of Sh. Jagdev Singh. The 70%
|
Comment: |