1 |
2021-10-01 00:00:00 Comment: The material to be used at site be tested as per norms and Test Reports be kept in record and shown to the audit team at the next visit.
R.C.C Mix be designed from any Engineering College or appr 5%
|
2022-01-03 00:00:00 Comment: At the time of visit work was in progress, but the speed of work on-going at site is very slow.
No approved structural drawing for the bus stand, duly vetted by any competent authority was provided b 30
|
2023-03-13 00:00:00 Comment: •At the time of visit work of excavation for foundations was in progress.
•The material to be used at site be tested as per norms and Test Reports be kept in record and shown to the audit team a 75%
|
Comment: |