2021-01-19 00:00:00 Comment: The material to be used for execution of work i.e. fine & coarse aggregates, I/L tiles &
bricks etc. should be got tested from NABL or Engineering college before its use.
For proper drainage the l 0%
|
2021-10-01 00:00:00 Comment: Test Reports for the materials being used at site not shown to the audit team.
Display board, showing description of work, estimated cost, specifications, executing agency’s name, date of start 30%
|
2021-10-01 00:00:00 Comment: Work of laying BM was in progress on 05.06.2021. Thickness of BM layer was
checked near Govt. Girls School and found to be in order as per provision of 50mm.
Work of laying PC was in progress on 70%
|
Comment: |