2020-11-12 00:00:00 Comment: Joints of brick masonry found hollow spaces. It needs to be rectified.
Bricks used in Brick masonry were not as per specifications. Partially burnt
bricks were used at site. Engineer in charge must 5%
|
2021-09-30 00:00:00 Comment: • Inner/ outer Joints of brick masonry were not filled as hollow spaces were visible.
• As per T&C of work order, the time period to complete the work has already been elapsed on 22.01.2021 and 30%
|
2021-03-15 00:00:00 Comment: Beam found cracked.
Slab casted had segregation.
Quality of bricks not adequate at some stretches. 70%
|