1 |
2020-11-10 00:00:00 Comment: Proposed site for closing of drain. 0%
|
2021-09-25 00:00:00 Comment: Near H.No. B-03/723 the cover of RG chamber was found damaged. Its needs to be replaced.
All the RG chambers constructed at site were clogged as they were filled with mud and malba, which has caused 45
|
2022-01-29 00:00:00 Comment: At the time of visit, the work was in progress at site. Closing of drain was in progress at site.
The dimension of hoddi constructed at site was checked at 02 random places and found 01’X01’. i.e 75%
|
Comment: |