Inspection Details

Column Filters

Work Details

Name of WorkClosing of drain in ward no 7,6,12,9,11,1 in different different street
Town NameGoniana
District NameBATHINDA
Approved Amount 50.2
Awarded Amount48.56
Award Letter Ref049/007 dt. 28.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-10 00:00:00
Comment: Proposed site for closing of drain.
0%
2021-09-25 00:00:00
Comment: Near H.No. B-03/723 the cover of RG chamber was found damaged. Its needs to be replaced. All the RG chambers constructed at site were clogged as they were filled with mud and malba, which has caused
45
2022-01-29 00:00:00
Comment: At the time of visit, the work was in progress at site. Closing of drain was in progress at site. The dimension of hoddi constructed at site was checked at 02 random places and found 01’X01’. i.e
75%


Comment: