Inspection Details

Column Filters

Work Details

Name of WorkP/Laying I.L.Pavers from Gau-shala to Kabristan.
Town NameBhadson
District NamePATIALA
Approved Amount 3.95
Awarded Amount3.6
Award Letter Ref2/50 dt. 24.09.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-09-30 00:00:00
Comment: work not started at the time of visit
0%
2020-12-29 00:00:00
Comment: For Earth filling having depth more than 1’ proper L-section & X-section showing the existing natural ground level (NGL) & final proposed level of earth filling be prepared & provided to the WAPCOS
30%
2021-09-30 00:00:00
Comment: Average thickness of lean concrete found 80mm instead of 100mm.
80%