1 |
2020-12-24 00:00:00 Comment: • At the time of visit work was not started at site.
• Existing site was katcha as the culvert is to be constructed on nala for movement of local people. 0%
|
2021-11-23 00:00:00 Comment: • At the time of the first visit, the work order provided was under contractor ‘Bela Co-op L/C Society’ with the Awarded cost as Rs. 14.21 lacs. Re-tendering was done, and a new work order was i 30%
|
Comment:
|
2022-04-08 00:00:00
Comment: • Dimensions of the Box culvert was checked at site and found as per the completion plan provided by the department.
• The date of starting of work of Construction of culverts near Golden City & 100% |