1 |
2020-12-10 00:00:00 Comment: Proposed site for laying of 60 MM I/L tiles. 0%
|
2020-12-24 00:00:00 Comment: • At the time of visit, work was in progress at site.
• During site visit it was found that 40 mm sand bedding was not being laid under i/l tiles as shown in pictures. It was further communicated 30%
|
Comment:
|
2022-05-14 00:00:00
Comment: • As per completion report/ certificate the work stands completed on 01.04.2021.
• The length of I/L tile paving marked as 390’ and 129’ 3” on completion plan checked and same as per comple100% |