2020-12-10 00:00:00 Comment: Proposed site for laying of 60 MM I/L tiles. 0%
|
2020-12-24 00:00:00 Comment: • At the time of visit the work of spreading of fine sand to fill joints of i/l tiles at park number 1 and Work of laying I/L tiles at the 2nd park was in progress at site.
• Out of the 5 parks a 30%
|
2021-10-14 00:00:00 Comment: • The berms/ footpaths around different parks were found paved with 60mm thick I/L tiles in Gilco Valley. • The thickness of bedding sand and lean concrete laid under 60mm thick I/L tiles checked 80%
|
2021-11-23 00:00:00
Comment: • As per completion report/ certificate the work stands completed on 26.02.2021.
• The length of I/L tiles paving around park no. 2 opposite #100 and park no. 3 opposite #73 was randomly checked 100% |