Comment:
|
2021-10-01 00:00:00 Comment: The thickness of PC was checked in bus stand and found in order.
The sealcoat observed not properly laid on PC.
No test reports of material used at site were provided by the department. 35%
|
2021-12-08 00:00:00 Comment: At the time of visit work was in progress.
No delivery sheets of batch type hot mix plant are provided to inspection team.
Test reports for the materials being used at site were not shown to the aud 75
|