Inspection Details

Column Filters

Work Details

Name of WorkLaying Inter locking Tiles in Baram Light Wala Chowk to Samad Left Side
Town NameJalabad
District NameFAZILKA
Approved Amount 25.44
Awarded Amount24.02
Award Letter Refnull
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-05-17 00:00:00
Comment: The proper record of compaction should be maintained & shown to WAPCOS team during the next visit.  For proper drainage the longitudinal slope and camber should be provided as per PWD specificat
0%
2021-06-19 00:00:00
Comment: Fine sand in the joints of I/L tiles should be filled for proper locking.  It was observed at site, that at some points I/L tiles paved surface was above the level of adjacent metalled road which
35%
2021-07-27 00:00:00
Comment: At the time of visit, work was in progress at site. The thickness of bedding sand and base concrete was checked in front of Damesh Rice Mills & Jagdish Rice Mills and found to be 25mm & 25mm (Sand),
75


Comment: