Name of WorkLaying Interlocking Tiles in St Pappu Doomra Wali Ward no 8
Town NameJalabad
District NameFAZILKA
Approved Amount 4.39
Awarded Amount3.9
Award Letter Ref15/5 Dt.14.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1
Comment:

2021-02-02 00:00:00
Comment: Display board, showing description of work, estimated cost, specifications, executing agency’s name, date of start of work, time of completion, name of the Technical Officer In-charge of work with
45%
2021-03-23 00:00:00
Comment: The thickness of bedding sand under I/L tiles flooring was checked randomly near First Choice Digital Printing Shop and found 15mm against the provision of 40mm, which is less than the required. The
70%