Name of WorkConstruction of Streets from Sugar Mill Road to H/o Husan Lal in ward No. 14, Nawanshahr.
Town NameNawansehar
District NameSBS Nagar
Approved Amount 6.68
Awarded Amount
Award Letter Ref
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1
Comment:

2021-10-03 00:00:00
Comment: Thickness of cc found 5inchs instead of 6inchs. RG chamber found 510mm instead of 800mm Top surface eroded. Time limit elapsed.
45%
2022-03-24 00:00:00
Comment: •Contraction & Expansion joints were not filled with polysulphide Sealant (as per estimate) due to which cracks have developed at some places. •Depth of R/G chamber was checked and found 510mm in
70%