2021-10-03 00:00:00 Comment: Work not started yet 0
|
2021-10-03 00:00:00 Comment: Thickness of cc was checked at site and found 3.5inchs. which not as per estimate.
RG chamber depth randomly checked at site and found 500mm instead of 800mm.
Expansion joints are not filled with se 45%
|
2022-03-24 00:00:00 Comment: •Contraction & Expansion joints were not filled with polysulphide Sealant (as per estimate) due to which cracks have developed at some places.
•Depth of R/G chamber was checked and found 500mm in 70%
|