Name of WorkConstruction of Different Street in Village Saloh in ward No. 5, Nawanshahr.
Town NameNawansehar
District NameSBS Nagar
Approved Amount 28.35
Awarded Amount26.84
Award Letter Ref14/8 dt. 24.12.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-03 00:00:00
Comment: Dismantling of existing surface completed
10
2021-10-03 00:00:00
Comment: Earth filling was completed. RG chamber construction Was in progress. Time limit for completion of work has been elapsed.
30%
2022-03-28 00:00:00
Comment: instead of 150mm as per provision. Concerned JE should make sure to check the thickness of CC before making any payment. •The dimensions of road gullies were randomly checked near Preet welding an
70%