Inspection Details

Column Filters

Work Details

Name of WorkP/L Interlocking tiles 80 mm and 50 mm Near Varindra Studio to Markit committee office (Left and Right Side) Bhaddi road, MC Balachaur
Town NameBalachaur
District NameSBS Nagar
Approved Amount 42.19
Awarded Amount40.71
Award Letter Ref50/1 dt. 23-12-2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-18 00:00:00
Comment: • At the time of visit, excavation work on sides was in progress where I/L tiles are to be paved. • Sub-base should be compacted properly before start of proposed work. • Proper record of comp
5%
2021-12-14 00:00:00
Comment: Thickness of bedding sand & lean concrete (1:8:16) under I/tiles was randomly checked near Krishan lal shop & found i.e. 100mm (Bedding sand : 40mm & lean concrete : 60mm ) Instead of 140mm (Be
50%

Comment:



Comment: