Name of WorkP/L Interlocking tiles 60 mm Madhiani Gate to Vinod PP Street MC Balachaur.
Town NameBalachaur
District NameSBS Nagar
Approved Amount 17.5
Awarded Amount17.06
Award Letter Ref13/2 dt 24.8.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-18 00:00:00
Comment: • At the time of visit, excavation work on sides was in progress where I/L tiles are to be paved. • Sub-base should be compacted properly before start of proposed work. • Proper record of comp
5%
2021-10-01 00:00:00
Comment: At the time of visit the work of laying of 60 mm thick I/L tiles was in progress.  Thickness of bedding sand and lean concrete was checked at site and found in order.  No test report of Int
30%
2021-12-14 00:00:00
Comment: The thickness of bedding sand & lean concrete (1:8:16) under 60mm I/tiles was randomly checked near Arra , thickness of bedding sand plus lean concrete was observed 125mm instead of 140mm,the
70%