2021-01-18 00:00:00 Comment: • Sub-base should be compacted properly before start of proposed work.
• Proper record of compaction and material being used at site should be maintained and shown to WAPCOS team during next visi 5%
|
2021-10-01 00:00:00 Comment: Thickness of bedding sand and lean concrete was checked at site. Lean concrete
was found to be 85 mmm. Concerned JE should check the thickness of bedding
sand and lean concrete as per contract spec 30%
|
2021-12-14 00:00:00 Comment: Thickness of bedding sand and lean concrete was checked at site.
Lean concrete was found to be 85 mm.
Concerned JE should check the thickness of bedding sand and lean concrete before
making any pa 70%
|