Inspection Details

Column Filters

Work Details

Name of WorkP/L Interlocking tiles 80 mm and 50 mm Berm Kagna pull to Khad Left and Right side MC Balachaur
Town NameBalachaur
District NameSBS Nagar
Approved Amount 10.32
Awarded Amount10.06
Award Letter Ref11/2 dt 24.8.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-01-18 00:00:00
Comment: • Proper X-sections should be prepared before starting the filling of earthwork (more than 01 feet) • Proper compaction should be done & the record of compaction should be maintained & shown to
5%

Comment:

2021-12-14 00:00:00
Comment: Proper compaction should be done & the record of compaction should be maintained & shown to WAPCOS team during the next visit. As per NIT, the time limit for the completion of work was 3 months i.e
70%


Comment: