2021-01-15 00:00:00 Comment: Proposed site for construction of kabristan. 2%
|
2021-10-02 00:00:00 Comment: • At the faces of some columns honeycombs were formed, may a reason of casting without vibrators/improper compaction of concrete. It needs to be repairing properly.
• At the time of visit constru 45%
|
2021-11-27 00:00:00 Comment: Some water taps and tap connections and faucet/jet connections were found broken in the toilet block. It needs to be rectified/replaced.
• During visit, no structural design was shown to TPA team, 85%
|
Comment: |