2020-12-09 00:00:00 Comment: The date of completion of work has already been lapsed as on 28.12.2020,
department must provide justification for not starting the work on time. 0%
|
2021-09-30 00:00:00 Comment: At the time of visit, laying of interlocking tiles
was in progress and interlocking tiles were
stacked at site
The Thickness of bedding sand + Lean concrete
randomly checked at one points 45%
|
2021-10-01 00:00:00 Comment: 60 mm ISI marked interlocking tiles were used at site.
The thickness of bedding sand under 60 mm thick interlocking tiles was checked and found 40mm.
The thickness of lean concrete under 80%
|