1 |
2020-12-09 00:00:00 Comment: Proposed site for P/L of I/L tiles. 5%
|
2021-09-30 00:00:00 Comment: At the time of visit, lean concrete was in
progress and interlocking tiles were stacked at
site
The depth of Road Galies was randomly
checked at three points and found as 720 mm,
610 mm a 30%
|
2021-10-01 00:00:00 Comment: „h 60 mm ISI marked interlocking tiles were used at site.
„h 60 mm ISI marked interlocking tiles were stacked at site.
„h The thickness of bedding sand was checked under 60 mm thick interlocki 80%
|
Comment: |