Name of WorkProviding/laying interlocking tiles in side berms in dasmesh colony, ward no. 9
Town NameRajpura
District NamePATIALA
Approved Amount 19.18
Awarded Amount17.6
Award Letter Ref2399 dt. 29.09.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-12-09 00:00:00
Comment: Proposed site for P/L of I/L tiles.
0%

Comment:

2021-12-23 00:00:00
Comment: As per NIT, the time limit for the completion of work was 2 months i.e up to date 24.10.2020, but the work is still in progress till date of inspection. No document for the extension of time limit wa
80


Comment: