Name of WorkRecarpetting/ strengthning of various roads of Guru Teg Bahadur colony, Dakala chungi to B&R quarters, Jagdish colony, Tej bagh colony, Desi Mehmandari in Ward no 30, 32, 33, 39, 51 Group - D
Town NameMC Patiala
District NamePATIALA
Approved Amount 145.11
Awarded Amount
Award Letter Ref
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-05 00:00:00
Comment: Work not started at the time of visit.  In new Sular colony, it was observed that the condition of existing Premix carpet is quite satisfactory & there is no necessity of laying fresh PC. 
0%
2021-09-30 00:00:00
Comment: 1) At the time of visit, the streets in Desi Mehmandari near #80 found paved with BC. Also near the #80 and #70, the BC pavement layer found damaged in an area about 15’x20’ which needs to be rect
45%
2021-10-01 00:00:00
Comment: Thickness of Bc found 33 mall manhole covered with bc No test report provided by department
75


Comment: