2021-01-27 00:00:00 Comment: At the time of visit the work of compaction of flooring of toilet block was in
progress.
The flooring of the toilet block is pending in both men and women toilet
blocks.
The panel adjacent to si 45%
|
2021-03-18 00:00:00 Comment: The flooring of the toilet block is pending in both men and women toilet blocks.
Fixing of WC was complete in men toilet block but no cistern is attached yet.
Jindal make heavy DT extra stro 70%
|
2022-03-22 00:00:00
Comment: The completion plan provided/submitted to WAPCOS was found without dimensions.
The grills were provided with Gates of Toilet block not painted, Wall Tiles were also found broken along with plaster.
100 |