1 |
Comment:
|
2021-01-27 00:00:00 Comment: At the time of visit the work of excavation of trenches for RG and laying of
pipes was in progress in street of Govt Elementary School.
The dimension of R/G was checked at various locations and fou 45%
|
2021-03-18 00:00:00 Comment: The dimension of R/G was checked at various locations and found proper. At some locations the
frames and cover of R/G are under size which should be replaced.
Groves are not properly cut as the 85%
|
2022-07-01 00:00:00
Comment: •The length of street randomly checked and found 150’ & 85’ as marked on completion plan provided.
•In the sanctioned estimate the rate of item of 4” thick M-30 grade CC flooring with CC 1100% |