1 |
2020-11-11 00:00:00 Comment: • At the time of visit Earth work in excavation of road gully was in progress. The existing streets were Katcha Streets.
• The sub base should be properly compacted before start of work.
5%
|
Comment:
|
2021-01-27 00:00:00 Comment: The dimension of R/G was checked in front of house of Gian Chand and
beginning of street & found proper.
The thickness of CC was checked in front of house of Joginder Architect and
open plot foun 80%
|
2022-03-22 00:00:00
Comment:
The depth of 03 Nos. R/G chambers were checked and found 760mm, 735mm & 735mm against 800mm as per CSR item No 29.92A(a). The average depth of the R/G chamber was found 743mm against 800mm. Necessar100 |