Inspection Details

Column Filters

Work Details

Name of WorkCC FLOORING ST UP WALA TO RAMESHWAR DAS JOSHIAND BABA BALKAR SINGH PANJPEER ROAD W-14
Town NameSamana
District NamePATIALA
Approved Amount 46.19
Awarded Amount40.24
Award Letter Ref8/35 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-11 00:00:00
Comment: • For Earth filling having depth more than 1’ proper L-section & X-section showing the existing natural ground level (NGL) & final proposed level of earth filling be prepared & provided to the WAP
0%
2021-01-27 00:00:00
Comment: The work of levelling and dressing of earth surface in street near open plots was in progress. Excavation of trenched near Somnath Kiryana store was in progress. The depth of CC laid was checked n
45%
2021-03-18 00:00:00
Comment: The depth of CC laid was checked near house of Sandeep Singh and found as 100 mm which is as per estimate.  Groves of CC was not filled with the sealing compound.  Finishing of surface must b
85%
2022-03-22 00:00:00

Comment: • The payment of this work was made partially from the PIDB grant for PUEIP-2 and from MC funds as informed by the MC Samana Officials present at the time of visit. But no proper details for the pay100