Name of WorkCC FLORING NEAR H/o SONU KULCHE WALA AND ST SURJIT SINGH
Town NameSamana
District NamePATIALA
Approved Amount 10.15
Awarded Amount8.54
Award Letter Ref8/33 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-11 00:00:00
Comment: • The existing streets were paved with cement concrete. The existing paving observed cracked/damaged in some portions, the camber/level was also not proper.
0%
2021-01-27 00:00:00
Comment: At the time of visit the work of dismantling of old street was in progress. At some location the dimensions of R/G was checked and found proper. SKT make frames and covers are being used at site. No
30%
2021-03-18 00:00:00
Comment: The MH cover was found settled near junction of street and observed that it is placed without frame rectification of the same must be done at the earliest to avoid any mis-happening.  Record of
85%
2022-03-22 00:00:00

Comment: The depth of 04 Nos. R/G chambers were checked and found 455mm, 455mm, 455mm & 510mm against 800mm as per CSR item No 29.92A(a). The average depth of the R/G chamber was found 470mm against 800mm. Nec100