2020-11-11 00:00:00 Comment: • The existing streets are paved with cement concrete. Some cracks & depression observed in some portions of the existing paving. 0%
|
2021-01-27 00:00:00 Comment: At the time of the work of dismantling of existing CC flooring was in progress.
The dimension of R/G was checked at various locations and found proper.
Record of test reports of material consumed 30%
|
2021-03-18 00:00:00 Comment: At site groves are cut at required intervals but not filled with sealing compound. During,
scrutiny of documents it was seen that item for grove cutting and filling was not taken in the
estimate pre 85%
|
2021-12-09 00:00:00
Comment: •As per MB No 215 Page 48 the date of completion of work is 07.02.2021. But as per work order the scheduled date of completion was 21.01.2021, which shows that the work was delayed about 17 days fro100% |