Name of WorkCC FLOORING AND R/G IN ST MANU TO HARIANT NAE AND ST NAND LAL
Town NameSamana
District NamePATIALA
Approved Amount 9.13
Awarded Amount8.92
Award Letter Ref8/30 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-11 00:00:00
Comment: • The existing streets were paved with cement concrete. Top surface of existing paving observed eroded /cracked in some portions.
0%
2021-01-27 00:00:00
Comment: At the time of the work of levelling of existing surface was in progress. The dimension of R/G was checked at various locations and found proper. Record of test reports of material consumed at site
30%
2021-03-18 00:00:00
Comment: At the time of the depth of CC laid was checked in the beginning of street and found as 100 mm which is as per estimate.  At site groves are cut at required intervals but not filled with sealing
85%
2022-03-22 00:00:00

Comment: No. 8/30 dt. 22.10.2020 The depth of 04 Nos. R/G chambers were checked and found 480mm, 405mm, 480mm & 560mm against 800mm as per CSR item No 29.92A(a). The average depth of the R/G chamber was fou100