2020-11-11 00:00:00 Comment: • The existing streets were paved with cement concrete. Top surface of existing paving observed eroded /cracked in some portions. 0%
|
2021-01-27 00:00:00 Comment: At the time of the work of levelling of existing surface was in progress.
The dimension of R/G was checked at various locations and found proper.
Record of test reports of material consumed at site 30%
|
2021-03-18 00:00:00 Comment: At the time of the depth of CC laid was checked in the beginning of street and found as 100 mm
which is as per estimate.
At site groves are cut at required intervals but not filled with sealing 85%
|
2022-03-22 00:00:00
Comment: No. 8/30 dt. 22.10.2020
The depth of 04 Nos. R/G chambers were checked and found 480mm, 405mm, 480mm & 560mm against 800mm as per CSR item No 29.92A(a). The average depth of the R/G chamber was fou100 |