Inspection Details

Column Filters

Work Details

Name of WorkC C FLOORING AND R/G IN ST SACHA MAHAN KLESHWAR MANDIR TO KAKA GUPTA
Town NameSamana
District NamePATIALA
Approved Amount 14.95
Awarded Amount14.61
Award Letter Ref8/29 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-11 00:00:00
Comment: • The existing streets are paved with cement concrete. The top surface of old paving observed eroded in some portions.
0%

Comment:

2021-01-27 00:00:00
Comment: At the time of visit no work was in progress. The depth of CC laid was checked near toilet and Mahakaal Temple and found as 100 mm which is as per estimate. The dimension of R/G was checked at var
80%
2022-03-22 00:00:00

Comment: The depth of 07 Nos. R/G chambers were checked and found 610mm, 555mm, 710mm, 760mm, 685mm, 530mm, & 530mm against 800mm as per CSR item No 29.92A(a). The average depth of R/G chamber was found 625mm 100