1 |
2020-11-11 00:00:00 Comment: • The existing street was paved with cement concrete. The camber of the existing paving observed not proper & some cracks/damages also observed at some points. 0%
|
Comment:
|
2021-03-18 00:00:00 Comment: At site groves are cut at required intervals but filled with cement sand mortar in ratio of 1:10 by
the contractor itself.
Finishing of CC laid was found proper.
Record of test reports of m 85%
|
2022-03-22 00:00:00
Comment: The depth of 02 Nos. R/G chambers were checked and found 430mm & 380mm against 800mm as per CSR item No 29.92A(a). The average depth of the R/G chamber was found 405mm against 800mm. Necessary recover100 |