2020-11-11 00:00:00 Comment: • If the old CC paving is dismantled, necessary credit for lean concrete under existing CC should be given to work. 0%
|
2021-01-27 00:00:00 Comment: At the time of the work of dismantling of existing streets was in progress.
The dimension of R/G was checked at various locations and found proper.
Plastering & Finishing of R/G chamber constructed 45%
|
2021-03-18 00:00:00 Comment: At some locations MH cover installed at site are without frames, which may get settled in
coming time period.
The top surface of CC is not properly finished as pug marks and segregation of aggre 85%
|