Inspection Details

Column Filters

Work Details

Name of WorkC C FLOORING AND R/G IN ST MOHINDER KUMAR EX MC
Town NameSamana
District NamePATIALA
Approved Amount 5.18
Awarded Amount5.04
Award Letter Ref8/25 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-11 00:00:00
Comment: • The existing road is Metalled road. Pot holes observed at some points on the existing road.
0%
2021-01-27 00:00:00
Comment: At the time of the work of dismantling was in progress. In street of satpal singh the work of levelling of surface was in progress. The work of construction of R/G chamber was in progress. Finishing
30%
2021-03-18 00:00:00
Comment: The groves are required to be cut to avoid cracks during expansion and contraction of concrete, whereas, at site the groves at required intervals are cut but not filled with sealing compound.  B
85%
2022-07-01 00:00:00

Comment: •In the sanctioned estimate the rate of item of 4” thick M-30 grade CC flooring with CC 1:8:16 2” thick was taken Rs 68.00/sqft whereas in the MB as well as in MW-12 the payment of CC M30 grade100%