Inspection Details

Column Filters

Work Details

Name of WorkC C FLOORING NEAR H/O JASWINDER SINGH KHATRIAN MOHALLA
Town NameSamana
District NamePATIALA
Approved Amount 13.61
Awarded Amount13.16
Award Letter Ref8/22 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-11 00:00:00
Comment: • The existing one street was paved with cement concrete & the other one was Katcha. The top surface of existing CC paving observed eroded in small patches.
0%
2021-01-27 00:00:00
Comment: At the time of the work of dismantling and levelling of surface was in progress. In street of Machar niwas the work of excavation of trenches for R/G chamber was in progress. Record of test repo
30%
2021-03-18 00:00:00
Comment: At site no vertical grove was cut, horizontal groves are cut at required intervals but not filled with sealing compound. During, scrutiny of documents it was seen that item for grove cutting and fil
70%
2022-03-22 00:00:00

Comment: • The payment of this work was made partially from the PIDB grant for PUEIP-2 as well as from MC funds as informed by the MC Samana Officials present at the time of visit. But no proper details for 100