2020-11-11 00:00:00 Comment: • The existing street was paved with cement concrete & found damaged/cracked in some portions. 0%
|
2021-01-27 00:00:00 Comment: The work of levelling of surface was in progress in street of Ram Babu.
At some location the dimensions of R/G was checked and found proper.
SKT make frames and covers are being used at site 30%
|
2021-03-18 00:00:00 Comment: At the time of the depth of CC laid was checked in the beginning of street and
found as 100 mm which is as per estimate.
At site groves are cut at required intervals but filled with cement sand 85%
|
2022-03-22 00:00:00
Comment: • The depth of 03 Nos. R/G chambers were checked and found 560mm, 560mm & 430mm against 800mm as per CSR item No 29.92A(a). The average depth of the R/G chamber was found 515mm against 800mm. Necess100 |