Inspection Details

Column Filters

Work Details

Name of WorkC C FLOORING NEAR H/O DHIAN MISTRI TO KASHMIR SINGH MALKANA PATTI W-7
Town NameSamana
District NamePATIALA
Approved Amount 4.85
Awarded Amount4.07
Award Letter Ref8/16 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-11 00:00:00
Comment: • At the time of visit the work was not started at site. • The existing street was paved with cement concrete & found cracked/damaged in some portions.
0%

Comment:

2021-01-27 00:00:00
Comment: Curing of CC laid was in progress. The depth of CC laid was checked near house of Shiv Charan Varita and found as 100 mm which is as per estimate. Groves of CC was not filled with the sealing compo
80%


Comment: