1 |
2020-11-11 00:00:00 Comment: • At the time of visit the work was not started at site.
• The existing streets were paved with cement concrete & found damaged/cracked in some portions.
0%
|
2021-01-27 00:00:00 Comment: At the time of visit the work of levelling of surface was in progress.
The dimension of R/G was checked and found proper.
The finishing of R/G chamber was proper.
Record of test reports of materia 45%
|
2021-03-18 00:00:00 Comment: The dimension of RG chamber was checked near H/O Santokh Singh & in its
Street and found in order.
Expansion & contraction joints were cut but not filled with sealing compound.
The top surf 85%
|
2022-03-22 00:00:00
Comment:
The length of the street marked as 133’8” & 20’ in the completion plan provided was checked and found same 133’8” & 20’ as marked in the completion plan.
Near the H/o Jagwinder Singh 100 |