1 |
2020-11-11 00:00:00 Comment: • At the time of visit the work was not started at site.
• The existing streets were Katcha.
• The sub base should be properly compacted before starting the proposed work.
0%
|
2021-01-27 00:00:00 Comment: The thickness of CC laid was checked near Sham lal house and found proper.
Three streets are yet to be finished.
Groves that are cut on CC was not filled with the sealing compound. During,
45%
|
2021-03-18 00:00:00 Comment: Finishing of CC must be ensured properly by the department at some locations
the top surface is unfinished and pug marks are visible. It must be rectified by the
department.
Record of test repo 85%
|
2022-03-22 00:00:00
Comment: he depth of 03 Nos. R/G chambers were checked and found 380mm, 480mm & 530mm against 800mm as per CSR item No 29.92A(a). The average depth of R/G chamber was found 463mm against 800mm. Necessary recov100 |