Inspection Details

Column Filters

Work Details

Name of WorkC C FLOORING IN ST MANOHAR LAL SHAM LAL BIJLIWALA AND CHAMKOR PRESS REPORTER
Town NameSamana
District NamePATIALA
Approved Amount 7.11
Awarded Amount6.95
Award Letter Ref8/12 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2020-11-11 00:00:00
Comment: • At the time of visit the work was not started at site. • The existing streets were Katcha. • The sub base should be properly compacted before starting the proposed work.
0%
2021-01-27 00:00:00
Comment: The thickness of CC laid was checked near Sham lal house and found proper.  Three streets are yet to be finished.  Groves that are cut on CC was not filled with the sealing compound. During,
45%
2021-03-18 00:00:00
Comment: Finishing of CC must be ensured properly by the department at some locations the top surface is unfinished and pug marks are visible. It must be rectified by the department.  Record of test repo
85%
2022-03-22 00:00:00

Comment: he depth of 03 Nos. R/G chambers were checked and found 380mm, 480mm & 530mm against 800mm as per CSR item No 29.92A(a). The average depth of R/G chamber was found 463mm against 800mm. Necessary recov100