1 |
2020-11-11 00:00:00 Comment: At the time of visit the work was not started at site.
The existing street was paved with cement concrete & found cracked/damaged in some portions.
0%
|
Comment:
|
2021-01-27 00:00:00 Comment: No vertical groves are cut on the CC laid as the work stands pending.
Groves that are cut on CC was not filled with the sealing compound. During,
scrutiny of documents it was seen that item for 70%
|
2022-03-22 00:00:00
Comment: • The depth of 05 Nos. R/G chambers were checked and found 610mm, 585mm, 585mm, 405mm & 610mm against 800mm as per CSR item No 29.92A(a). The average depth of the R/G chamber was found 560mm against100 |