2020-11-11 00:00:00 Comment: • At the time of visit the work was not started at site.
The existing street was paved with cement concrete & observed cracked in some portions.
0%
|
Comment:
|
2022-05-20 00:00:00 Comment: Curing of CC laid was in progress. The depth of CC laid was checked near house of Bharat
kumar and found as 100 mm which is as per estimate.
Groves of CC was not filled with the sealing compound. D 85%
|
2021-12-09 00:00:00
Comment: •The depth of 02 Nos. R/G Chamber near the H/o Charan Das & 02 nos. R/G chambers near H/o Kala Ram was checked and found 355mm, 508mm, 330mm and 355mm respectively. Hence the average depth of R/G C100% |