2021-10-04 00:00:00 Comment: Work is not started 0%
|
2021-01-27 00:00:00 Comment: The work of dismantling of old surface was in progress in street of Prem chand.
The excavation of trench for R/G was in progress.
Proper gradient in R/G must be ensured by the department for efficie 30%
|
2021-03-18 00:00:00 Comment: The thickness of CC laid at site was checked at various locations and found as 100 mm which is
as per estimate.
The dimensions of RG was checked t various location and found as average 450 x 570 70%
|