1 |
2021-10-04 00:00:00 Comment: Work is not started 0%
|
2021-01-27 00:00:00 Comment: The work of levelling of surface was in progress in street of Vivekananda ashram.
The excavation of trench for R/G was in progress in Pala Hotel Street.
Proper gradient in R/G must be ensured by the 45%
|
2021-03-18 00:00:00 Comment: The excavation of trench for R/G was in progress in Pala Hotel Street.
Proper gradient in R/G must be ensured by the department for efficient flow.
Dimension of constructed R/G was checked a 70%
|
2022-07-01 00:00:00
Comment: •At the time of visit it was observed around 90% area of CC flooring top surface was found eroded and was not up to the mark.
•In the sanctioned estimate the rate of item of 4” thick M -30 gra100 |