1 |
2021-10-04 00:00:00 Comment: Work is not started 0%
|
2021-01-27 00:00:00 Comment: At the time of visit the work of dismantling of existing street was complete.
The work of levelling of earth surface was in progress in street of Balwainder
Singh.
Proper levelling of the surface 30%
|
2021-03-18 00:00:00 Comment: At the time of visit the work of laying of DB was in progress.
The gap between the joints of bricks was found more than 10 mm which
should be rectified.
The surface was firmly levelled and 70%
|
Comment: |