1 |
2021-10-04 00:00:00 Comment: Work is not started 0%
|
2021-01-27 00:00:00 Comment: At the time of visit the work of dismantling of existing CC Street was complete.
The work of levelling of earth surface was in progress in street of Lakhwinder Singh.
The dimension of RG chamber was 30%
|
2021-03-18 00:00:00 Comment: The dimension of RG chamber was checked near gaushala and Lakhwinder
Singh Street and found in order.
At present 21 RG was constructed at site having PVC pipe of 8’’ dia connected
for dispo 70%
|
2022-03-22 00:00:00
Comment: • The depth of 05 Nos. R/G chambers were checked and found 510mm, 560mm, 585mm, 510mm & 530mm against 800mm as per CSR item No 29.92A(a). The average depth of the R/G chamber was found 540mm against100 |