2021-10-04 00:00:00 Comment: Work is not started. 0%
|
2021-01-27 00:00:00 Comment: At the time of visit the work of dismantling of existing street was in progress.
The work of levelling of earth surface and excavation for RG was in progress in
street no-1.
Proper levelling of th 30%
|
2021-10-05 00:00:00 Comment: The thickness of bedding sand and lean concrete was checked and found as 40
mm and 100 mm which is as per estimate.
60 mm ISI mark “SKT” make I/L tiles were being laid at site.
SKT make 70%
|