1 |
2021-10-04 00:00:00 Comment: Work is not started. 0%
|
2021-01-27 00:00:00 Comment: At the time of visit the work of dismantling of existing street was in progress.
The work of levelling of earth surface was in progress in street no-3.
Proper levelling of the surface must be ensure 30%
|
2021-09-23 00:00:00 Comment: At the time of visit, the street No 4 of Partap colony was found paved with I/L tiles of 60mm thickness and ‘SKT’ make.
Near h.no. 85/8, the thickness of bedding sand under I/L tile of 60mm thick 80
|
2022-07-01 00:00:00
Comment: •Incomplete Annexure A (Defect rectification) has provided by MC officials. Many points/comments which had mentioned in earlier reports by WAPCOS have not taken in Annexure A and no compliance on th100% |