Inspection Details

Column Filters

Work Details

Name of WorkP/L INTERLOCKING TILES NEAR H/O SATISH KUMAR EO
Town NameSamana
District NamePATIALA
Approved Amount 4.15
Awarded Amount2.73
Award Letter Ref7/91 dt. 22.10.2020
Sr.No First Visit Progress Second Visit Progress Third Visit Progress Fourth Visit Progress
1 2021-10-04 00:00:00
Comment: Work Is not Started.
0%

Comment:

2021-01-27 00:00:00
Comment: At the time of visit, no work was in progress at site.  Sand filling to fill the joints of I/L tiles laid was not done properly. Department must ensure that sand filling in the joints should be
80%


Comment: